PUD approves five year utility rate increases

Costs for power, water, sewer and internet services provided by the Chelan PUD will be going up June 1, 2027.
PUD commissioners on Monday adopted a five-year incremental rate adjustment strategy to reduce the reliance on uncertain energy market sales to cover future operating expenses..
"When we went through the 50-year visioning process, we started to analyze what the role of the energy market is in covering operational costs, and the fact is that the energy market is changing," Rachel Hansen, PUD senior communications strategist said. "Part of the motivation fot this five-year rate plan is to cover our operational costs in a way that doesn't lean so heavily on revenues from selling surplus hydropower. And, we would like to become more self sustainable over time."
“As we, as a community of people, are struggling with finances, I really struggled with the idea of a rate increase,” Commissioner Steve McKenna said. “When we look 50 years out at closing the gap we have on production, there are some things we need to do to assure we’re running a great organization in the long run for our customers.”
Overall, the PUD’s financial outlook remains strong. The proposed budget, to be considered by commissioners at a meeting Dec. 7, forecasts $567 million in revenue and a $169 million bottom line, which is $45 million better than the adopted 2026 budget. The biggest contributor of revenue is surplus hydropower contracts, which increased after Chelan PUD replaced a portion of the Alcoa contract with smaller market-based slice contracts.
Total operating expenses across the utility are projected at $413 million including depreciation and taxes, which is about $39 million above the 2026 budget. The budget includes power system upgrades, wildfire protection, expanded fiber service and the monthly financial settlement of the Canadian Entitlement allocation of the Columbia River Treaty.
The budget also includes about $188 million in capital investment. Rock Island Dam work represents the largest portion of hydro dam investments, including modernization of generating units at Powerhouses 1 and 2, the drop gate structure, and electrical system upgrades.
Chelan PUD is planning to build new substations as community needs grow, including Bavarian substation in Leavenworth and two substations in Wenatchee — Bridge Street and Castlerock. The PUD also plans to upgrade College Substation in Wenatchee and Leavenworth Substation.
Wildfire resiliency is another major focus. Chelan PUD is planning a steel rebuild of an existing high-voltage transmission line between Peshastin and Coles Corner near Lake Wenatchee. The design and proposed contract are expected to come before commissioners in fall 2027, with construction planned in 2028.
Here’s how the proposed rate plan would impact residential customer bills, based on average usage:
Electricity: 5% annual increase, or about $3.50 more on the average monthly bill.
Water: 2.5% annual increase, or about $2 more on the average monthly bill.
Wastewater: 4% annual increase, or about $4 more on the average monthly bill.
Wholesale fiber, 2.5% annual increase deferred for 2027.
Details on the five-year rate plan can be found here.




Informative coverage explaining utility rate changes and their financial impact. A best call recording app helps businesses securely record, store, and review important phone conversations. It supports better communication management, improves team accountability, tracks customer interactions, and allows users to revisit call details for accurate documentation and enhanced service quality.