US 97A (MP 202) ½ Mile S. of Rocky Reach Dam
MONDAY THROUGH FRIDAY, 8:30a.m. to 4:30p.m., expect weekday road closures for 14 days, ending by Mar. 26th. Daily traffic openings are scheduled from 10a.m. to 10:30a.m., Noon to 12:30p.m. and 2p.m. to 2:30p.m. (then, no restrictions overnight from 4:30p.m. to 8:30 a.m. )
In this $3.1 million project, Janod Inc. crews are scaling an unstable rock slop and installing netting, rock bolts and dowels along the slope 2 miles north of Wenatchee.. Construction began Feb. 21, 2012 and should be complete by June.
Project Engineer: Bob Romine (509) 667-2880.